Project:
Replacement of equipment in the existing old heating plant within the ZAGREB INTERNATIONAL AIRPORT. Mechanical, construction and electrical works in the 15 MW boiler room (the main contractor).
Investor:
Zagreb International Airport
Location:
Velika Gorica / Pleso
End of project:
2019
Types of work:
- Construction of the new gas boiler room of total capacity 14.4 MW (two 4.2MW boilers and an existing old boiler with a new 6 MW burner)
- Execution of construction works during reconstruction
- Execution of electrical works including automation (boiler room operation and connection to the existing central supervision and management of the Airport)
Other details:
We disassembled the old equipment in only three months (mechanical equipment, construction equipment, electrical equipment). We installed the new equipment, launched the plant into operation and successfully performed technical inspection.