01 3098 360 [email protected]

We made this!

Plastform

Plastform, Sesvete

Construction of steam boiler room in the Plastform facility

Grafika Radin

Execution of works on the construction of heating and cooling systems on the Sveta Nedjelja facility

TOWN OF GLINA

Heat pipe construction within ”Glina Remote Heating System” project

Drvni centar Glina

Wood center Glina

Heat pipe construction and mechanical installations in pulp and biomass drier

Sušara Slatina

Slatina DRIER

Boiler room and heat pipe installation

Babina Greda

Uni Viridas, Babina Greda

Installation of ventilation and air-conditioning system – 10 MW cogeneration plant

FUNTANA CAMP

Reconstruction of hot water preparation system

Vertiv

VERTIV DATA CENTRES

Mechanical works on HVAC installations in data centre construction project

Šipan

LUXURY VILLAS

Mechanical works on heating, cooling and ventilation installations for a luxury villa complex

Jaskapak

Jaškapak

Mechanical works on construction of steam boiler room

Hilton, Zagreb

Mechanical works on the installation of heating and cooling within the construction project of Hilton and HT business facilities

Turopolje

ORC Pana, Turopolje

Installation of factory mechanical equipment in 1 MW cogeneration plant

BELIŠĆE COGENERATION

Construction of gassification-cogeneration plant

Jaskapak

Jaškapak

Overall steel construction of steam boiler room

Slatina DRIER

Production and installation of steel elements for connecting energy plant with drier

Wood center Glina

Steel grid construction in pulp and bio mass drier construction project